Construction process in 90 days
We optimize every phase of the process, from design to assembly, ensuring a sustainable and efficient home.
Day 01.
Layout of the foundation slab once the plot has been prepared and cleared
Day 05.
Formwork and concreting of foundation slab according to geotechnical study parameters
Day 15.
Assembly of laminated wood supporting structure according to project
Day 30.
OSB/3 panel perimeter cladding for façade and roof bracing
Day 45.
Passage of light and water installations without the need for grooves
Day 50.
Waterproofing of the roof using two layers of self-protected, heat-sealable asphalt fabric
Day 60.
Day 65.
Supply and installation of Tivek vapor barrier film for ventilated façades
Day 70.
Supply and installation of facade finishes
Day 75.
Day 80.
Custom-made wardrobes
Day 85.
Custom kitchen design